C W Sellors Carsington - Site Visit 26.04.23

Jewellery & Watch News

We can’t believe it has been 9 months since construction began on our new Carsington home and despite some cold weather, the team at G F Tomlinson have been able to get on with their build schedule. We managed to make the most of some rare sunshine this week to record our latest drone footage. With the main steel structure completed, the work on the insulation panelling has been clearly visible before work starts on the walling. This week also saw the start of the glass windows being installed.

If you'd like to stay informed on the progress of our C W Sellors National Gemstone & Jewellery Design Centre at Carsington, stay updated on our News page here.